2023 Road Paving Project beginning August 28, 2023

2023 Road Paving Project beginning August 28, 2023.

Please be advised that the following road work will begin the week of August 28, 2023 (dates are weather permitting)

 

  • August 28th, 29th, and 30th – first application of chip seal
    • Barrington Lane
    • Fairfield Drive
    • Fairfield Drive North
    • Parkview Lane
    • Greenbriar Lane
  • August 28th, 29th, and 30th – double bituminous chip seal application
    • Saucon Avenue
    • West Rock Road (From Heckmans to Douglas)
    • Douglas Road
    • Ironwood Lane
    • Lanze Lane
    • Woodland Hills Drive
    • Birchwood Drive
    • Dogwood Lane
  • August 31st – polymer modified fog seal application
    • Woodland Hills Drive
    • Birchwood Drive
    • Dogwood Lane
  • September 11th and 12th – type II slurry seal application
    • Barrington Lane
    • Fairfield Drive
    • Fairfield Drive North
    • Parkview Lane
    • Greenbriar Lane